Storage efficiency node
The reference storage node, RefStorage, does not include any efficiencies for the stored Resource. It is always assumed that there is no associated loss of the stored Resource when charging or discharging the storage. StorageEfficiency nodes are introduced to enable storage efficiency control compared to Storage.
The nodes utilize the parametric implementation for all storage nodes and the individual capacities for charge and storage level.
Introduced type and its fields
The StorageEfficiency{T} is implemented as a subtype of EMB.Storage{T}, extending the existing Storage node.
The fields of a StorageEfficiency are:
id:
The fieldidis only used for providing a name to the node.charge::EMB.UnionCapacity:
The charging parameters of theStoragenode must include a capacity. Depending on the chosen type, thechargeparameters can also include variable OPEX and/or fixed OPEX.level::EMB.UnionCapacity:
The level parameters of theStoragenode must include a capacity.. Depending on the chosen type, thechargeparameters can also include variable OPEX and/or fixed OPEX.Permitted values for storage parameters in `charge` and `level` If the node should contain investments through the application of
EnergyModelsInvestments, it is important to note that you can only useFixedProfileorStrategicProfilefor the capacity, but notRepresentativeProfileorOperationalProfile. Similarly, you can only useFixedProfileorStrategicProfilefor the fixed OPEX, but notRepresentativeProfileorOperationalProfile. The variable operating expenses can be provided asOperationalProfileas well. In addition, all capacity and fixed OPEX values have to be non-negative.stor_res::ResourceEmit:
Thestor_resis the storedResource.input::Dict{<:Resource,<:Real}andoutput::Dict{<:Resource,<:Real}:
Both fields describe theinputandoutputResources with their corresponding conversion factors as dictionaries. The storedResource(outlined above) must be included to create the linking variables.data::Vector{<:Data}:
An entry for providing additional data to the model. In the current version, it is used for additional investment data whenEnergyModelsInvestmentsis used.
Mathematical description
In the following mathematical equations, we use the name for variables and functions used in the model. Variables are in general represented as
$\texttt{var\_example}[index_1, index_2]$
with square brackets, while functions are represented as
$func\_example(index_1, index_2)$
with paranthesis.
Variables
Standard variables
The storage efficiency node types utilize all standard variables from the RefStorage{T} node type, as described on the page Optimization variables. The variables include:
- $\texttt{opex\_var}$
- $\texttt{opex\_fixed}$
- $\texttt{stor\_level\_inst}$
- $\texttt{stor\_level}$
- $\texttt{stor\_charge\_inst}$
- $\texttt{stor\_charge\_use}$
- $\texttt{flow\_in}$
- $\texttt{flow\_out}$
- $\texttt{stor\_level\_Δ\_op}$
- $\texttt{stor\_level\_Δ\_rp}$ if the
TimeStructincludesRepresentativePeriods
It does not add any additional variables.
Constraints
The following sections omit the direct inclusion of the vector of StorageEfficiency nodes. Instead, it is implicitly assumed that the constraints are valid $\forall n ∈ N$ for all StorageEfficiency types if not stated differently. In addition, all constraints are valid $\forall t \in T$ (that is in all operational periods) or $\forall t_{inv} \in T^{Inv}$ (that is in all investment periods).
Standard constraints
StorageEfficiency utilize in general the standard constraints that are implemented for a Storage node as described in the documentation of EnergyModelsBase. These standard constraints are:
constraints_capacity:\[\begin{aligned} \texttt{stor\_level\_use}[n, t] & \leq \texttt{stor\_level\_inst}[n, t] \\ \texttt{stor\_charge\_use}[n, t] & \leq \texttt{stor\_charge\_inst}[n, t] \end{aligned}\]
constraints_capacity_installed:\[\begin{aligned} \texttt{stor\_level\_inst}[n, t] & = capacity(level(n), t) \\ \texttt{stor\_charge\_inst}[n, t] & = capacity(charge(n), t) \end{aligned}\]
Using investments The function
constraints_capacity_installedis also used inEnergyModelsInvestmentsto incorporate the potential for investment. Nodes with investments are then no longer constrained by the parameter capacity.constraints_level:
The level constraints are more complex compared to the standard constraints. They are explained in detail below in the description on level constraints inEnergyModelsBase.constraints_opex_fixed:\[\begin{aligned} \texttt{opex\_fixed}&[n, t_{inv}] = \\ & opex\_fixed(level(n), t_{inv}) \times \texttt{stor\_level\_inst}[n, first(t_{inv})] + \\ & opex\_fixed(charge(n), t_{inv}) \times \texttt{stor\_charge\_inst}[n, first(t_{inv})] \end{aligned}\]
Why do we use `first()` The variables $\texttt{stor\_level\_inst}$ are declared over all operational periods (see the section on capacity variables for further explanations). Hence, we use the function $first(t_{inv})$ to retrieve the installed capacities in the first operational period of a given investment period $t_{inv}$ in the function
constraints_opex_fixed.constraints_opex_var:\[\begin{aligned} \texttt{opex\_var}&[n, t_{inv}] = \\ \sum_{t \in t_{inv}}& opex\_var(level(n), t) \times \texttt{stor\_level}[n, t] \times scale\_op\_sp(t_{inv}, t) + \\ & opex\_var(charge(n), t) \times \texttt{stor\_charge\_use}[n, t] \times scale\_op\_sp(t_{inv}, t) \end{aligned}\]
The function `scale_op_sp` The function $scale\_op\_sp(t_{inv}, t)$ calculates the scaling factor between operational and investment periods. It also takes into account potential operational scenarios and their probability as well as representative periods.
constraints_data:
This function is only called for specified data of the storage node, see above.
Even if a Storage node includes the corresponding capacity field (i.e., charge, level, and discharge), we only include the fixed and variable OPEX constribution for the different capacities if the corresponding storage parameters have a field opex_fixed and opex_var, respectively. Otherwise, they are omitted.
The functions constraints_flow_in and constraints_flow_out are extended with new methods that, compared to a RefStorage node, better controls the storage efficiency:
The function constraints_flow_in is exytended with a new method to incorporate the conversion factor also for the stored resource. The effective charging rate is defined by the conversion factor (typically <1) of the stored resource $p_{\text{stor}}$:
\[\texttt{stor\_charge\_use}[n, t] = \texttt{flow\_in}[n, t, p_{\text{stor}}] \times inputs(n, p_{\text{stor}})\]
For each additional input resource $p ∈ inputs(n) \setminus p_{\text{stor}}$, the flow is proportional to the main storage flow by a conversion factor:
\[\texttt{flow\_in}[n, t, p] = \texttt{flow\_in}[n, t,p_{\text{stor}}] \times inputs(n,p)\]
The function constraints_flow_out is extended with a new method to incorporate the conversion factor for discharging_
\[\texttt{flow\_out}[n, t,pstor]=\texttt{stor\_discharge\_use}[n, t] 'times outputs(n, p_{\text{stor}})\]
This models energy losses when discharging from storage (e.g., thermal or round-trip losses in batteries).